Productivity Analysis of Pile Driving Equipment in Mumbai

International Journal of Civil Engineering
© 2017 by SSRG - IJCE Journal
Volume 4 Issue 5
Year of Publication : 2017
Authors : Prakash H. Panda, Mr. Sahajanand Kamat
pdf
How to Cite?

Prakash H. Panda, Mr. Sahajanand Kamat, "Productivity Analysis of Pile Driving Equipment in Mumbai," SSRG International Journal of Civil Engineering, vol. 4,  no. 5, pp. 57-65, 2017. Crossref, https://doi.org/10.14445/23488352/IJCE-V4I5P122

Abstract:

Modern construction projects are complex in nature and success of a project depends greatly on proper and scientific planning. Proper use of appropriate equipment contributes to economy, quality, safety, speed and timely completion of the project. One of the most important tasks in the pre-construction planning process is equipment selection. Productivity has for many years been an issue for the construction industry. The industry is deeply concerned that construction productivity is not only below that of the manufacturing sector, but is also below the national average. The industry has identified several factors that have impeded construction productivity, namely, a shortage of suitably trained, skilled supervisors and workers; a weakening local construction workforce. Often when data become available, the site condition has changed and the improvement ideas obtained from productivity analysis are already obsolete. Timely productivity monitoring can provide construction engineers with insightful information so that corrective measures can be applied immediately to control on-going construction. Various analytical and simulation productivity analysis models were identified, studied and compared in view of their suitability. After the proper understanding of all these various models definitive steps can be taken to choose among the best available pile driving machinery for best output with good economy. Also a certain degree of validation is established among the various methods.

Keywords:

Productivity, Construction operations, Method productivity delay model (MPDM), Time lapse, Five minute rating, Field survey Rating, Piling, Relative Importance Index.

References:

1) Shi, J. J, "Activity-based construction (ABC) modeling and simulation method", J. of Constr.Engrg. And Mgmt., ASCE, Vol. 125, No. 5, pp. 354-360, 1999. 137_WD2.
2) Halpin, D. W., and Riggs, L. S., Planning and Analysis of Construction Operations, Wiley,New York, 1992.
3) Lutz, J. D., Halpin, D. W., and Wilson, J. R., "Simulation of learning development in repetitive construction", J. of Constr. Engrg. And Mgmt., ASCE, Vol. 120, No. 4, pp. 753-773,1994.
4) Abraham Assefa TSEHAYAE and Aminah Robinson FAYEK ―A Research Framework for Work Sampling and its Application in Developing Comparative Direct and Support Activity Proportions for Different Trades
5) James J. Adrian, LeRoy T. Boyer(1976) ―Modeling Method Productivity
6) Indian Brand Equity Foundations, Construction Equipment Market ―Productivity Improvement of Pre-cast Concrete Installation Souma M. AlhajAli ,Ayman A. Abu Hammad, Ghaleb J. Sweis) and Murad S. Samhouri
7) Productivity in Construction‖ by Dozzi, S.P.; AbouRizk, S.M.
8) CONSTRUCTION OPERATION SIMULATION TOOL – COST by Tao-ming Cheng, Shien-Tang Wu, and Yi-Wei Tseng
9) Evaluation of Factors Affecting on Construction Equipment Acquisition Methods in Malaysia by Masoud Navazandeh Sajoudi , Mohammadali Kazerooni Sadi, Arham Abdullah, Mohammadreza Kasraei, HodaRezaie
10) Estimation of Optimal Productivity in Labor-Intensive Construction Operations by Krishna Prasad Kisi
11) Construction Labor Productivity and its Improvement by M.C. Thiyagu, Mr. M. Dheenadhayalan
12) Pile Construction Productivity Assessment by Tarek M Zayed, Daniel W Halpin.