Lean Operations Management Model to Increase On-Time Project Delivery in a Construction Company

International Journal of Civil Engineering
© 2023 by SSRG - IJCE Journal
Volume 10 Issue 4
Year of Publication : 2023
Authors : Juan Carlos Quiroz-Flores, Friedman Acuña-Cervantes, Angelica Quicaña-Arbieto, S. Nallusamy
pdf
How to Cite?

Juan Carlos Quiroz-Flores, Friedman Acuña-Cervantes, Angelica Quicaña-Arbieto, S. Nallusamy, "Lean Operations Management Model to Increase On-Time Project Delivery in a Construction Company," SSRG International Journal of Civil Engineering, vol. 10,  no. 4, pp. 22-28, 2023. Crossref, https://doi.org/10.14445/23488352/IJCE-V10I4P104

Abstract:

The construction industry is exposed to more significant risks and unforeseen events than other industries, as projects are often developed under unpredictable circumstances due to different factors that must be taken into account during their execution. In addition, delays in the construction industry are considered one of the biggest problems faced by projects, as they can lead to cost overruns, disputes between parties, project abandonment and even lawsuits. The objective of the present study aims to increase the on-time delivery of construction projects by addressing the reasons and root causes identified in the study. The innovative proposal to avoid project delivery delays is introducing a Lean system based on the Last Planner System (LPS) methodology, designed to support production planning and control in construction projects. The proposed model was validated using a pilot plan in a project of tracks and greenways carried out in Lima, obtaining; as a result, a decrease of 8% in the time of project delays with respect to the initial deadline, an increase of 22% in the percentage of the completed plan and a decrease of 5% of the stoppages due to rework. The research confirms the success of the lean construction philosophy and its powerful tools, such as the LPS, which will serve as a reference for its application in other companies with similar characteristics.

Keywords:

LPS, Construction projects, Lean construction, Planning, Lean management.

References:

[1] Global Data: How will Latin American Construction Perform in 2022?, Peru Construye, 2022. [Online]. Available: https://peruconstruye.net/2022/04/21/global-datacomo-se-desempenara-la-construccion-latinoamericana-en-2022/
[2] GDP First Quarter 2020, National Institute of Statistics and Informatics, 2020. [Online]. Available: https://www.inei.gob.pe/media/MenuRecursivo/boletines/informe_tecnico_pbi_i_trim2020.pdf
[3] GDP First Quarter 2021, National Institute of Statistics and Informatics, 2020. [Online]. Available: https://www.inei.gob.pe/media/MenuRecursivo/boletines/04-informe-tecnico-pbi-iii-trim-2021.pdf
[4] M Kh Saidova, Sh I Xodjimuxamedova, and M A Dadarbaev, “Improvement of the Material and Production Resources Control in the Construction Industry,” IOP Conference Series: Materials Science and Engineering, vol. 919, no. 4, pp. 1-8, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[5] Mohammed Adel Abdelmegid et al., “Exploring the Links between Simulation Modelling and Construction Production Planning and Control: A Case Study on the Last Planner System,” Production Planning & Control, vol. 34, no. 5, pp. 459-476, 2023.
[CrossRef] [Google Scholar] [Publisher Link]
[6] Lauri Koskela, Theory of Lean Construction, 1 st Edition, Lean Construction: Core Concepts and New Frontiers, Taylor and Francis, London, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[7] Aneetha Vilventhan, VG Ram, and S Sugumaran, “Value Stream Mapping for Identifying and Assessing Material Waste in Construction: A Case Study,” Waste Management and Research, vol. 37, no. 8, pp. 815-825, 2019.
[CrossRef] [Google Scholar] [Publisher Link]
[8] William Power, Derek Sinnott, and Patrick Lynch, “Evaluating the Efficacy of a Dedicated Last Planner System Facilitator to Enhance Construction Productivity,” Construction Economics and Building, vol. 21, no. 3, pp. 142-158, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[9] J. Millán, Delays in the Construction Industry: The Case of the State of Mexico, Autonomous Mexico State University, 2015.
[10] Zahra Mohammadnazari, and Seyed Farid Ghannadpour, “Sustainable Construction Supply Chain Management with the Spotlight of Inventory Optimization under Uncertainty,” Environment, Development and Sustainability, vol. 23, no. 7, pp. 10937-10972, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[11] Flora Bamana, Nadia Lehoux, and Caroline Cloutier, “Simulation of a Construction Project: Assessing Impact of Just-in-Time and Lean Principles,” Journal of Construction Engineering and Management, vol. 145, no. 5, 2019.
[CrossRef] [Google Scholar] [Publisher Link]
[12] Gunji Venkata Punna Rao, S. Nallusamy, and M. Rajaram Narayanan, “Augmentation of Production Level Using Different Lean Approaches in Medium Scale Manufacturing Industries,” International Journal of Mechanical Engineering and Technology, vol. 8, no. 12, pp. 360-372, 2017.
[Google Scholar] [Publisher Link]
[13] Chia-Nan Wang, Ngoc-Ai-Thy Nguyen, and Thanh-Tuan Dang, “Solving Order Planning Problem Using a Heuristic Approach: The Case in a Building Material Distributor,” Applied Sciences, vol. 10, no. 24, p. 8959, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[14] Xueying Wu et al., “Improving the Efficiency of Highway Construction Project Management Using Lean Management,” Sustainability, vol. 11, no. 13, 2019. [CrossRef] [CrossRef] [Google Scholar] [Publisher Link]
[15] Ramani, P. V., and KSD, L. K. L., “Application of Lean in Construction Using Value Stream Mapping,” Engineering, Construction and Architectural Management, vol. 28, no. 1, pp. 216-228, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[16] B.A.K.S. Perera, D.C. Sirimewan, and A.D. Senadeera, “Management of Variations in the Public-Sector Building Construction Projects in Sri Lanka,” Journal of Engineering, Design and Technology, vol. 19, no. 6, pp. 1601-1619, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[17] Osama Abusalem, “Towards Last Planner System Implementation in Gaza Strip, Palestine,” International Journal of Construction Management, vol. 20, no. 5, pp. 367-384. 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[18] Min Gao et al., “Study on the Mechanism of a Lean Construction Safety Planning and Control System: An Empirical Analysis in China,” Ain Shams Engineering Journal, vol. 14, no. 2, pp. 1-18, 2023.
[CrossRef] [Google Scholar] [Publisher Link]
[19] Qian Chen et al., “Using Look-Ahead Plans to Improve Material Flow Processes on Construction Projects When Using BIM and RFID Technologies,” Construction Innovation, vol. 20, no. 3, pp. 471-508, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[20] Jianyu Zhao et al., “Using Real-Time Tracking of Materials and Labor for Kit-Based Logistics Management in Construction.”, Frontiers in Built Environment, 7, 122., 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[21] Soufiane El Moussaoui et al., “Construction Logistics Centers Proposing Kitting Service: Organization Analysis and Cost Mapping,” Buildings, vol. 11, no. 3, p. 105, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[22] A. Latorre Uriz, C. Sanz, and B. Sánchez, “Application of Lean-BIM Model to Improve Design Building Phase's Productivity,” Construction Reports, vol. 71, no. 556, p. e313, 2019.
[CrossRef] [Google Scholar] [Publisher Link]
[23] Weiqi Xing et al., “Implementing Lean Construction Techniques and Management Methods in Chinese Projects: A Case Study in Suzhou, China,” Journal of Cleaner Production, vol. 286, p. 124944, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[24] M. Suresh, and R.B. Arun Ram Nathan, “Readiness for Lean Procurement in Construction Projects,” Construction Innovation, vol. 20, no. 4, pp. 587-608, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[25] Mohamed Saad Bajjou, and Anas Chafi, “Lean Construction and Simulation for Performance Improvement: A Case Study of Reinforcement Process,” International Journal of Productivity and Performance Management, vol. 70, no. 2, pp. 459-487, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[26] V. Saravanan, S. Nallusamy and Abraham George, “Efficiency Enhancement in a Medium Scale Gearbox Manufacturing Company Through Different Lean Tools - A Case Study,” International Journal of Engineering Research in Africa, vol. 34, pp. 128-138., 2018.
[CrossRef] [Google Scholar] [Publisher Link]
[27] V. Saravanan, S. Nallusamy, and K. Balaji, “Lead Time Reduction through Execution of Lean Tool for Productivity Enhancement in Small Scale Industries,” Intnational Journal of Engineering Research in Africa, vol. 34, pp. 116-127, 2018.
[CrossRef] [Google Scholar] [Publisher Link]
[28] Jeffrey Boon Hui Yap et al., “Criticality of Project Knowledge and Experience in the Delivery of Construction Projects,” Journal of Engineering, Design and Technology, vol. 20, no. 3, pp. 800-822, 2022.
[CrossRef] [Google Scholar] [Publisher Link]
[29] Soumi Majumder, Soumyajit Majumder, and Debasish Biswas, “Impact of Effective Construction Planning in Project Performance Improvement,” Quality and Quantity, vol. 56, pp. 2253-2264, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[30] G. A. Howell, A Guide to the Last Planner™ for Construction. Foremen and Supervisors, Lean Construction Institute, 2021. [Online]. Available: https://leanconstruction.org/lean-topics/last-planner-system/
[31] W Fazinga et al., “Implementation of Standard Work in the Construction Industry,” Construction Engineering Magazine, vol. 34, no. 3, pp. 288-298, 2019.
[CrossRef] [Google Scholar] [Publisher Link]